GROUND AND PROCESSED SPICES
The project will take atleast 6 months to come into operation for which the implementation schedule has been worked out as follows: 1. Preparation of project 1 month report, selection of site, registration as SSI unit 2. Availability of finance, 23 months selection of machinery and procurement of machinery 3. Erection and commis 34 months ...